After this week on Maisto Mountain, Brad and I feel like our building structure really looks like a house! Midday on Monday (Aug. 24), the roof trusses arrived for the home. Biggins Construction set the trusses on Tuesday with a crane and has spent the week putting the roof decking on as well as beginning to build out our porches. On Thursday (Aug. 27), the windows arrived from Obermeier Do It Best Hardware in Rockport, and the windows were installed on Thursday. We have the size and structure of Maisto Mountain in place! Brad and I are both very happy with what we see and pleased with the work. Our next steps are that the crew will finish the framing. Then our metal siding and roofing can be placed on the outside of the home. Brad also is meeting with interior contractors regarding our plumbing and electrical work. We have made some exciting progress this week! | |